CHILLICOTHE, Ohio — U.S. Paper Mill crews worked through the weekend to keep contaminated groundwater beneath the city’s east side from rising after a key containment well failed last week, the company said in a news release.
A decades-old shaft fractured inside Well 18, one of the wells U.S. Paper Mill uses to pump water and hold back a plume of chemicals left behind by the former WearEver manufacturing plant, which closed in the 1990s. The company said it notified the Ohio Environmental Protection Agency and the city of Chillicothe as soon as the malfunction was discovered and began looking for a fix.
Because replacing the fractured shaft could not be done quickly, the company shifted to Well 17, which had been sitting dormant. U.S. Paper Mill said that well is now pumping and the water table is being maintained, containing the plume as before.
U.S. Paper Mill has operated the pumping system voluntarily since acquiring the closed former WearEver site last year, the release said, describing the work as a service to the Ohio EPA and Howmet to keep the water table from rising into the contaminated plume. Employees check the wells on hourly rounds every shift and perform maintenance on pumps that the company said cost at least $1 million a year to operate.
The company said its commitments at the site also include receiving and processing leachate from the Paint Street Landfill, maintaining compliance with state water flow and air quality permits, and eliminating odor through the closure of the former pulp mill.
“I am grateful to all our colleagues who prioritized the health and safety of the community we love over the operations of our business,” Utility Superintendent Aaron Anders said in a statement. “We are pleased to see that the well water is being pumped, and we will continue to monitor the situation, as we always have.”
The information contained in this story was obtained from U.S. Paper Mill.